Team Status Report for April 29th

Team Status Report for April 29th

Our biggest problem has been lighting for the CV. As always, it detects the balls’ shadows as part of the ball, meaning that with poor or uneven lighting, it can merge two balls together or even fail to detect a ball since the shape is 

Team Status Report for April 22nd

Team Status Report for April 22nd

This week, Justin worked on resoldering the components using softer wire. He also made some updates so that the pool cue will also send the direction it is facing when a shot is made. Devank made some changes to the frame to allow the webcam 

Team Status Report for April 8th, 2023

Team Status Report for April 8th, 2023

This week, Justin worked on soldering the components so they are more stable when attached to the pool cue. He also worked on integration by making it so his data can be printed to a txt file, which can then be read by our other 

Team Status Report, April 1st 2023

Team Status Report, April 1st 2023

This week the team continued on making significant progress. Jimmy further optimized his CV system to account for color detection, and Jimmy and Devank were able to integrate their separate systems. Devank was able to fix an error pointed out by Jimmy this week with 

Team Status Report For March 25th, 2023

Team Status Report For March 25th, 2023

This Week was Really Good in terms of progress for the team. Devank finished a preliminary bug-free shot calculation that can find the optimal shot given a random game state. Jimmy got the CV system to work and is able to detect pool balls and 

Team Status Report for March 18, 2023

Team Status Report for March 18, 2023

This week was mostly spent by the team working on the group ethics assignment and on our individual parts. All 3 subsystems are making significant progress and we are still on track with our schedule. The only significant risk to the project right now is 

Team Status Report for March 11

Team Status Report for March 11

This week was mostly spent working on the frame and Design Report. Now that the wood had arrived, since it was already behind, we spent most of the time building the frame to catch up. An early photo of our in-progress frame. More supports have 

Team Status Report for February 25

Team Status Report for February 25

Currently there is some risk resulting from delays in materials coming in. We just received the wood for the frame which was behind schedule. We are managing this risk by going out of order on our schedule and working on the software before we get 

Team Status Report for February 18th

Team Status Report for February 18th

For significant risks, two team members have been sick last week and this week so if this is to continue over the rest of the semester it could cause problems. We are managing these risks by trying to stay as safe as possible for staying 

Team Status Report for February 11th

Team Status Report for February 11th

Currently the most significant risk that we face is a delay in getting the parts for us to use. These are being managed by us making back up plans in case we don’t get the parts. There have been no changes yet to the existing