Team Status Report for March 11

This week was mostly spent working on the frame and Design Report. Now that the wood had arrived, since it was already behind, we spent most of the time building the frame to catch up.

An early photo of our in-progress frame. More supports have since been added to make it more stable.

Currently there are no major risks, now that the rest of our supplies have come in. There is the risk of being unable to fit the projector on our frame, but we have enough spare wood to create extra support systems. There have been no changes to our design or schedule. Everything is proceeding within our expectations.