Ian Brito’s Weekly Status Report for 2/25

At the beginning of this week, I presented our design presentation. For the rest of this week, most of the work was ordering my part (RPi) from ECE inventory and working on the web app. I created the Django web app, but do not yet have it looking like the mock up. Additionally, I looked at the Design Report to start thinking about what to write in it.

I would say that currently, my progress in on schedule based on the new schedule from the design presentation which we updated after we pivoted our project. We had planned for most of this week to be ordering parts, starting work on web app (me), and generally working on the project idea. After receiving feedback on Friday, I thought of ways we could increase the scope of our project, such as adding more sensors or adding complexity to the web app.

The deliverables that I am looking to get done next week are the Design Report, as well as getting the web app running on the RPi. I want to get both of these tasks done before Spring Break so that our group is on schedule.

We have adjusted team work assignments to fill in gaps by recreating our schedule as stated above to account for the late(ish) pivot in our project. Because our schedule was created fairly recently (last week), we were able to plan accordingly.

Leave a Reply

Your email address will not be published. Required fields are marked *