Team Status Report for 02/26/2022

Currently the significant risk that we are facing is figuring out where to do the rendering now. It risks an architecture change. We have multiple contingency plans and are currently evaluating the risk/reward/effort of all of these (we are meeting again tomorrow to finalize our decision).

The most important task for the project at this stage is to address the above and get some MVP form of Scotty3D running so we can complete other tasks.

No changes were made to the schedule, as we believe we can catch up during Spring Break and with some hopefully provided slack days. Changes to the system design have not been made for now.