This week, I prepared for the ethics discussion and finished adjusting the wire length of all of the electrical components. I ordered the junction box to enclose the electrical components early last week, but Amazon removed the item from its website, so I had to order a similar item. This delayed the arrival of the junction box by a week, and I just received it today.
The junction box arrived a week later than expected, which delayed the testing process. I am planning on testing the sensor data accuracy/lag to make sure that our sensors meet our greenhouse requirements with Kanon as soon as possible. Sarah is also planning to install the camera and RPi onto the greenhouse next week, so we are planning on integrating the camera into the greenhouse system soon.