Team Status Report 3/27

This week we experienced some major setbacks as we had not yet received all the parts we had ordered. Due to this, we were not able to set up all the hardware components we had previously planned on developing. In light of this, we focused on the iOS application and were able to create both login and sign-up pages. In the coming week, we will begin to work on both the hardware components and enclosure for our system.