This week I worked on writing the design report. We divided up the report according to how we divided the proposal and design presentations. I worked on the project management aspects as well as the user interface of the presentations, so I wrote those sections of the proposal. I wrote the schedule, division of labor, introduction, budget, user interface, and IR frame design trade-off sections. After we each wrote our individual sections, we met together to combine everything and format it all correctly. In addition to this, this week we started to receive the parts for our mirror. We have already received the Jetson Xavier NX, Arducam, and monitor, and we are still waiting on the mirror. Next week, we will begin assembling the mirror.