Team Status Report for 4/12

After our demo, our team decided that we would work on finishing up loose ends on our individual components. This included (1) porting the song selection algorithm from python to java, (2) porting the audio modification component to C++, and (3) writing code that would break up a song into 60 second chunks before warping. This would allow us to start integration the following week.

We made this decision based on our conversation with Professor Sullivan and Jens as they heavily reemphasized our goals for the end of the project. Additionally, we realized that our work progress was behind in relation to our Gantt chart. According to the plans, we would have completed integration this week and would move on to extended features in our following two weeks of slack time.

Thus, we will take what we have so far, integrate, and continue advancing on our individual parts in the remainder of our slack time, and then integrate again.