Weekly Status Report – 05/04

Bhuvan’s status report (May 4, 2019)

This week, I finished up the final steps of the application layer. Mainly working on last minute testing for the demo on Monday. After the demo will put in the final changes to the design report.

Dhruva’s Status Report (May 4, 2019)

This week, I had the presentation which went smoothly. My work is mostly done. Once Bhuvan is done with the application layer integration, our capstone will be ready for demo.

Raziq’s Status Report (May 4, 2019)

This week has been relatively calm. The datalink layer is pretty much set at this point, and I have identified the necessary parameters to reach our benchmarks. I’ve also helped tweak the digital filtering on the input pins for better accuracy of reception.

Upcoming work

Record and upload demo video

Present capstone demo

Finish and submit final report

Team Status Report

We are working together on completing the remaining deliverables. This weekend will be for wrapping up for the public demo and for recording the video. We have also started the final report, which we will revise on Tuesday and Wednesday before submitting.