Status Report 03-09 (zbp)

My accomplishments this week:

  • Most of the week spent preparing for design review and writing our report
  • Got rev. 1 mostly ready for ordering. Changelog as follows:
    • Added silks
    • Rerouted some of the ribbon connections
    • Increased the size of tracks on some nets
    • Repoured power plane to use direct contact (no relief)
    • Moved some traces around to reduce impedance on MCU power lines

My personal deliverables for next week:

  • Board actually ordered
  • Status onĀ getting caught up-to-speed with the state of firmware development (ft. Stan and Cameron) while waiting for the board and BOM to arrive

Updates on last week’s deliverables:

  • Version control migration done
  • Board pending review as of Friday (2 days behind schedule, Gantt chart has been pushed back into slack slightly)