My accomplishments this week:
- Most of the week spent preparing for design review and writing our report
- Got rev. 1 mostly ready for ordering. Changelog as follows:
- Added silks
- Rerouted some of the ribbon connections
- Increased the size of tracks on some nets
- Repoured power plane to use direct contact (no relief)
- Moved some traces around to reduce impedance on MCU power lines
My personal deliverables for next week:
- Board actually ordered
- Status onĀ getting caught up-to-speed with the state of firmware development (ft. Stan and Cameron) while waiting for the board and BOM to arrive
Updates on last week’s deliverables:
- Version control migration done
- Board pending review as of Friday (2 days behind schedule, Gantt chart has been pushed back into slack slightly)