Team status report for 09/25

This week we worked on practising for the proposal presentation. After the proposal presentation, we began finalizing implementation details for our project. We thought about whether we should use Arduino or Rpi. We were going with RPi earlier but found that other teams had integration troubles with it. We met 3 times to figure out the details of each part of the project like LEDs, chessboard, CV, AI etc. The objective of the final meeting was to place order on equipment that we need. We also placed our order for a sample chessboard that we can get chess pieces from and also use to test our CV. We placed an order for an attachable logitech camera with 1280 x 720 resolution. 

 