Somya’s Status Report for 3/16/2024

What did you personally accomplish this week on the project? Give files or

photos that demonstrate your progress. Prove to the reader that you put sufficient

effort into the project over the course of the week (12+ hours).

This week I attached all the sensors onto the glove and worked on implementing/testing the circuit. After performing unit tests and discussing an expanded range in our weekly meeting, we determined that op-amp use would be the way to go, and through use of op-amps we managed to expand the voltage output from 0.8V to 2V. 

 

Is your progress on schedule or behind? If you are behind, what actions will be

taken to catch up to the project schedule?

My progress is on  schedule. 

 

What deliverables do you hope to complete in the next week? 

 

Now that we are in the data collection phase, I want to do some more research into how we can clean up the data with noise reduction algorithms. In addition, I would like do some more research on the Bluetooth data transmission so we can more on that in parallel along with the data collection, as well as fabrication of glove 2