This week’s accomplishments

  • Wrote, edited, and formatted the design report. Specifically, these were my responsibilities on the report:
    • hardware architecture
    • Introduction
    • gantry subsystem implementation
    • water heating and distribution subsystem implementation
    • scale subsystem implementation
    • risk mitigation
    • BOM
    • Formated, edited, and submitted the final report
  • Attended mandatory lab
  • Pump flow and current testing
    • will need to test further to fully understand the relation between current and flow rate.

Next week’s plan (spring break)

  • Will be traveling, so I have limited time to work hands-on with the project
  • However, will be looking to successfully run OctoPrint on my personal Rpi to communicate with the 3-D printer
  • Experiment with different flow rates (and how much current each rate requires)

Status Report: On schedule