Week of Apr 7 – Apr 13
Administrivia
- N/a
Project
Worked on other things (as part of the schedule for build week). Thought about how to make the IR better, as well as ways to improve on the RFID.
Scheduling
I am behind schedule now. Next week I will grind to get back on schedule.
New Schedule | |
Dates | Task |
Feb 4 – Feb 6 | Come up with a first draft of the bill of materials for three cars |
Feb 6 – Feb 8 | Started design of RFID and IR circuits |
Feb 8 – Feb 15 | Started design the physical layout of a car |
Feb 15 – Feb 22 | Finish first draft of circuit designs |
Feb 22 – Feb 25 | Design the PCB that goes in the car |
Feb 25 – Feb 28 | Find appropriate battery and power system parts |
Feb 28 – Mar 3 | Work on preparing for the design review presentation and report |
Mar 3 – Mar 9 | Finish first draft of 3D model for the car |
Mar 17 – Mar 19 | Assemble frame. |
Mar 19 – Mar 25 | Build IR circuits, get started on RFID and Xbox controller and assemble 2 cars. |
Mar 25 – Mar 31 | Finish the IR circuits so that they are mountable and work on Xbox controller inputs. Also, prepare for midpoint demo. |
Mar 31 – Apr 4 | Optimize the RFID scanner, make third car. |
Apr 4 – Apr 9 | Optimize the RFID scanner, make third car. |
Deliverables for Next Week:
- Next week, be done with my individual tasks and ready to integrate everything.
Bujji’s Status Report: Week 8