Week of Apr 28 – May 4

Administrivia

  • N/a

Project

This week I was able to complete most of the tasks I had said I was going to do last week:

  • Fix the IR circuits to have pull down resistors on the inputs to the OR gates.
  • Built all three cars.
  • Redid the wheels to have rubber band caps so that the wheels don’t fall off.
  • Added extra sponges to prevent damage to the cars.
  • Covered the wheels in Cello tape so they experience less torsional force.
  • Did a lit bit of cable management so not as many wires are coming out.

Scheduling

Just got to prepare for the demo on Monday

Deliverables for Next Week:

  1. Full system testing and debugging
Bujji’s Status Report: Week 11