Week of Mar 23 – Mar 30
Administrivia
Had to work on and turn in the second ethics assignment.
Project
This week I worked on a few different things to help get the project ready for our midpoint demo next week:
- IR: Finished the IR transmitter and receiver circuits enough for the demo. I have come to realize that a PCB is not as expensive as I originally thought, and would make the manufacturing of the cars go much faster. Additionally, I did as many circuit optimizations as I could improve the distance for reception of IR pulses, and it seemed that 8ft was the best I could get with goo accuracy. I have some ideas as to some high level changes I could make that might have some benefits. I will explore these after the midpoint demo.
- Frame and assembly: I changed the designs for the car so that the following issues will no longer be a problem:
- The motor housing slots were about an 1/8″ too tight, so I need to increase the spacing of those.
- I can narrow down on the width of the battery base and rpi base parts to reduce weight and complexity.
- Should remove the outer hexagons of the honeycomb heat sink as they get covered up by the battery base anyway.
- Move the Camera housing stands outward so they don’t cover the output ports of the battery packs.
I also assembled most of one car so that we will be ready to demo on Wednesday:
Scheduling
I am on track for my tasks
New Schedule | |
Dates | Task |
Feb 4 – Feb 6 | Come up with a first draft of the bill of materials for three cars |
Feb 6 – Feb 8 | Started design of RFID and IR circuits |
Feb 8 – Feb 15 | Started design the physical layout of a car |
Feb 15 – Feb 22 | Finish first draft of circuit designs |
Feb 22 – Feb 25 | Design the PCB that goes in the car |
Feb 25 – Feb 28 | Find appropriate battery and power system parts |
Feb 28 – Mar 3 | Work on preparing for the design review presentation and report |
Mar 3 – Mar 9 | Finish first draft of 3D model for the car |
Mar 17 – Mar 19 | Assemble frame. |
Mar 19 – Mar 25 | Build IR circuits, get started on RFID and Xbox controller and assemble 2 cars. |
Mar 25 – Mar 31 | Finish the IR circuits so that they are mountable. Prepare for midpoint demo. |
Mar 31 – Apr 4 | Optimize the RFID scanner, make third car. |
Apr 4 – Apr 9 | Slack |
Deliverables for Next Week:
- PCB design for IR circuits.
- Prepare for demo.