Progress

This week we continued to finish up the specification feature set and expand from what we had at the midterm demo. Jens is working on expanding the polyphony voices and finishing up the core synthesis pipeline, Hailang has been working on the wavetables and tuning the effects chain, and Charles has been working on adding ADSR envelopes to the synthesis pipeline while he waits for parts to arrive. We anticipate to fully integrate our feature specification next week, as Hailang and Jens will finish the synthesis pipeline and Charles can finish constructing his filters.

Scheduling

The main risk at this point in time is if the analog filter or amplification stages do not perform to specification. We have enough time to compensate and course adjust if issues arise, but it will delay finishing testing until we can isolate the issue and/or find new parts. The parts we use are all designed for audio applications though, so we do not think there will be any major issues there. All that will be left is testing and evaluation according to the metrics we had set.

Leave a Reply

Your email address will not be published. Required fields are marked *