Team Status Report for 11/30/24

It has been two weeks since the last status report. In the first week, we completed the interim demo. Then, we started working on integrating our three subsystems. The eye-tracking to application pipeline is now finished and the application to hardware integration is very close to finished. 

There are still some tasks to complete for full integration: The eye tracking needs to be made more stable, and the CAD model for the solenoid case needs to be completed and 3D-printed. We suspect there are some issues with STM32cubeIDE settings when we attempt to integrate UART to dynamically control solenoids based on parsed MIDI data. 

Our biggest risk right now is not finishing testing. Our testing plans are extensive (see last week’s team report), so they will not be trivial to carry out. Since we have a shorter time frame to complete them than expected, we might have to simplify our testing plans, but that would not be optimal.