Team Update for 11/2/2024

General Update

This week Josh spent time programming the esp to interface with a general purpose computer via BLE communication to view force readings from the sensors. Alex worked mainly on the mobile app, namely continuing work from the previous week focused around the app’s startup sequence and data visualization aspects.

Risks and risk mitigation

No additional risks (to those previously mentioned) were found during this week’s work.

overall design changes

No design changes.

schedule

The schedule remains the same as we are on track.

GANTT Chart