Katherine’s Status Report for 04/18

ACCOMPLISHED: 

This week, we worked on our final presentation. We went through feedback from the last presentation and decided we needed better documentation for software tradeoffs and software system structure. We also created plan for user surveys as oppose to full on user testing. This rescoping was necessary because we are still working on software firmware integration, and hardware firmware integration.

PROGRESS / SCHEDULE:

My progress is on schedule.  However, we are a few days behind integration, which is why we needed to rescope our testing plan.

DELIVERABLES / NEXT STEPS:

Next Week, I will:

  • Finish final presentation
  • Begin working on final deliverables
  • User test