This week I prepared for our teams design presentation and presented it. I also started to do work on devising a scheme for organizing and batching IMU data in the embedded system.
I am on schedule.
Next week I will receive the parts to be able to start implementing some of the protocols and give Geronimo some foundation to start coding the receiving end of the IOS application. I have been slightly blocked this week but we have accounted for this in the GANTT chart. Next week I will implement my data batching scheme and output data via bluetooth. I will also work on completing a test suite that will show metrics of the working system.