Yon’s Status Report for 02/08/2025

This week I mostly prepared for our proposal presentation. This meant I worked with my teammates on coming up with our semester’s Gantt chart based on my assessments of my own responsibilities and the dependencies we have on each other’s work. I believe we are on schedule, as we have just created the schedule.

Next week we plan on placing an order that is relevant to all of our subsystems – the scanner – so I plan on providing some input as to the purchase and looking over my teammates recommendations and needs. I also plan on getting started on parametrizing the math from V. Skala and R. Pan via the parameters we plan on optimizing.