This week, we received and put together the PCB prototypes, started code for the bracelet, and worked on the webapp.
- What are the most significant risks that could jeopardize the success of the project? How are these risks being managed? What contingency plans are ready?
One risk is that the plastic wrap still hasn’t come in, so the interim demo bracelet might need to be fabricated entirely out of plastic tubing or have no plastic covering. The casing isn’t a major subsystem, so we should be fine without casing for the interim demo anyways. BLE setup/interfacing is also challenging, but will be addressed after the interim demo when integrating the bracelet and web app.
- Were any changes made to the existing design of the system (requirements, block diagram, system spec, etc)? Why was this change necessary, what costs does the change incur, and how will these costs be mitigated going forward?
No changes were made to the existing design of the system. Soon after the interim demo, we may consider changing requirements or other design elements if feedback suggests that it would benefit the system.
- Provide an updated schedule if changes have occurred.
The Gantt chart has been updated to reflect that complete (separate) subsystems of the physical bracelet and webapp are due April 1st (interim demo).
- This is also the place to put some photos of your progress or to brag about a component you got working.
Isn’t it beautiful? Let’s hope it actually works.