Erin’s Status Report Week of March 16

What did you personally accomplish this week on the project? Give files or photos that demonstrate your progress. Prove to the reader that you put sufficient effort into the project over the course of the week (12+ hours).

This week, I worked on bluetooth code for the app side. I was able to create a bluetooth manager object in the app and a tester page for it. Using that I was able to work with Alan to connect the app to the arduino. To do this I also had to set up the app onto my iPhone which took some additional time.

• Is your progress on schedule or behind? If you are behind, what actions will be taken to catch up to the project schedule?

On schedule

• What deliverables do you hope to complete in the next week?

Over the next week, I plan on writing more of the app for the bluetooth page as well as more of the backend data structure for the app.