This week I focused mostly on the design review report and ordering equipment for the ampere-maxwell experiment. For the report, I worked on the ampere-maxwell experiment section in the Design trade studies and system implementation section, as well as the Test, Verification and validation section and the Project Management section. For the project management section, it was helpful to create the bill of materials table that helped us to define our expenditure and budget.

Our progress is on schedule as we have received the materials we ordered. In the next week, I will implement the Ampere-Maxwell Experiment with the materials I have received. This will be a mockup of the circuit (actual equipment but not soldered or installed fully for presentation purposes).