Anita’s Status Report for 04/08

Anita’s Status Report for 04/08

What did you personally accomplish this week on the project? Give files or photos that demonstrate your progress. Prove to the reader that you put sufficient effort into the project over the course of the week (12+ hours).  This week was the interim demo. It 

Anita’s Status Report for 04/01

Anita’s Status Report for 04/01

What did you personally accomplish this week on the project? Give files or photos that demonstrate your progress. Prove to the reader that you put sufficient effort into the project over the course of the week (12+ hours).  So I started off the week integrating 

Anna’s Status Report for 04/01

Anna’s Status Report for 04/01

What did you personally accomplish this week on the project? Give files or photos that demonstrate your progress. Prove to the reader that you put sufficient effort into the project over the course of the week (12+ hours).   This week, I continued working on the 

Team Status Report for 04/1

Team Status Report for 04/1

What are the most significant risks that could jeopardize the success of the project? How are these risks being managed? What contingency plans are ready? The most significant risk as of right now is linking the backend PDA with the front end web application. This 

Kelly’s Status Report for 4/1

Kelly’s Status Report for 4/1

What did you personally accomplish this week on the project? Give files or photos that demonstrate your progress. Prove to the reader that you put sufficient effort into the project over the course of the week (12+ hours).  This week, I took a deep dive 

Anita’s Status Report for 3/25

Anita’s Status Report for 3/25

What did you personally accomplish this week on the project? Give files or photos that demonstrate your progress. Prove to the reader that you put sufficient effort into the project over the course of the week (12+ hours).  This week was admittedly a bit of 

Team Status Report for 03/25

Team Status Report for 03/25

What are the most significant risks that could jeopardize the success of the project? How are these risks being managed? What contingency plans are ready? Right now, a big risk for our team is completing pitch detection integration with the web application. This element of 

Anna’s Status Report for 03/25

Anna’s Status Report for 03/25

What did you personally accomplish this week on the project? Give files or photos that demonstrate your progress. Prove to the reader that you put sufficient effort into the project over the course of the week (12+ hours).   This week, for capstone, we spent part 

Kelly’s Status Report for 3/25

Kelly’s Status Report for 3/25

What did you personally accomplish this week on the project? Give files or photos that demonstrate your progress. Prove to the reader that you put sufficient effort into the project over the course of the week (12+ hours).  This week, I ramped up to the 

Anna’s Status Report for 03/18

Anna’s Status Report for 03/18

What did you personally accomplish this week on the project? Give files or photos that demonstrate your progress. Prove to the reader that you put sufficient effort into the project over the course of the week (12+ hours).   This week, we worked on the ethics