This week I made very good progress. I got the CV program working with the video and have experimented with the optimization of it to make it work faster. I also have worked on the detection of solids vs stripes vs the eight ball vs the cue ball. The image below shows a white circle around the cue ball, a black circle around the 8 ball, green circles around solids and a red circle around the striped ball.

I am currently on schedule. This week I am planning on finishing implementing the color for the video(it should just be a simple case of changing thresholds to account for a difference in camera) and then integrating my program with the backend shot calculation. This should go quickly as Devank and I have discussed extensively the communication between the two.