Team Status Report For 04/29/2023

Team Status Report For 04/29/2023

The significant risk that could jeopardize the success of the project right now is that we haven’t integrated our system yet and each team member is still working on perfecting our individual parts. To manage this risk, we will be dedicating the majority of the 

Team Status Report for 4/22

Team Status Report for 4/22

The most significant risk that could jeopardize the success of the project currently are the accuracy of our wait time algorithm and how to transfer the data from our Jetson to our database SQLite. Now that Nii has almost finished his duties, he will be 

Team Status Report for 04/08/2023

Team Status Report for 04/08/2023

We believe that the current most significant risk that could jeopardize the success of the project is that we are still working on integrating the hardware and software parts which means performance and accuracy are still our main concerns because we aren’t sure what the 

Team Status Report for 04/01

Team Status Report for 04/01

The most significant risks that could jeopardize the success of the project is probably the hardware component because we received the Jetson Nano so close to the interim demo and was experiencing trouble setting it up in the beginning of the week (this problem has 

Team Status Report for 3/25

Team Status Report for 3/25

The most significant risks that could jeopardize the success of the project is that we have trouble setting up the hardware side which leads to us having trouble integrating the whole system together. We are concerned about this because it’s difficult to estimate the current 

Team Status Report for 3/18

Team Status Report for 3/18

The most significant risks which could jeopardize the success of our project thus far are a lack of integration of parts too late in the semester. Currently we are all developing our parts individually, but bringing it all together is what is most important for 

Team Status Report for 03/11/2023

Team Status Report for 03/11/2023

As a team, the week was mostly spent on doing the design review report. We were still waiting on some hardware components to arrive so that we could finally start setting them up in public space. We think the risks that could jeopardize the success 

Team Status Report for 02/25/2023

Team Status Report for 02/25/2023

The camera we decided on previously – the Sainsmart IMX219 – is not a USB camera as we had indicated previously, as has been pointed out in the feedback. However, as it is compatible with the Jetson Nano board in which our image processing algorithm 

Team Status Report for 02/18/23

Team Status Report for 02/18/23

Referring back to our team status report from last week, we mentioned that not having our design flow fleshed out before the design review was a significant risk that could jeopardize the success of the project. This issue has been resolved as we spent a 

Team Status Report for 2/11/23

Team Status Report for 2/11/23

The most significant risks that could jeopardize the success of the project are us not having our design flow fleshed out before the design review. This is why this week we focused on sub portions of each of our tasks. By doing this, when we