What did you personally accomplish this week on the project?
In the week leading up to break I focused on completing the design report. Specifically I worked on the scheduling/task division and fleshing out the architecture, system implementation and design trade studies for the mobile interface application. This involved doing further research into Apple’s CoreBluetooth Framework and determining a generalised system architecture for the application. In addition to this, I completed the design trade study and system implementation for the device enclosure. I also started drafting some initial designs.
Is your progress on schedule or behind? If you are behind, what actions will be taken to catch up to the project schedule?
I did not have much opportunity to make progress on the project over the past couple of weeks due to midterms and commitments over spring break. However, I had accounted for having less time in the first couple of weeks of March earlier in the semester and plan to set aside a large amount of time to make progress in the coming weeks.
What deliverables do you hope to complete in the next week?
This week I hope to have more sketches of the device enclosure completed, as well as the model classes for the application finalised. If I have additional time I plan on working on creating customised views for the application