This week, I worked on building out the full frontend view of our application, including charts and form settings. On the home page, I finalized the screen design and fixed … Read More “Dina Razek’s Status Report for March 19, 2022”
status report
Sam Lavelle’s Status Report for Mar. 19, 2022
This week I collected all of our supplies that had come in and reserved a bin to hold them. We recieved our 2 RPis, RFID reader for testing, and accessory … Read More “Sam Lavelle’s Status Report for Mar. 19, 2022”
Team Status Report for March 19th
This week, the team worked on the ML for our wait time estimation, web application development, and circuit development. We received feedback on our Design Report that helped us stay … Read More “Team Status Report for March 19th”
Sophie Sacks’s Status Report for March 19th
This week, I personally made a great deal of progress on the machine learning model in the backend of our web application. I began by creating some mock training data … Read More “Sophie Sacks’s Status Report for March 19th”
Team Status Report for February 26th, 2022
This week, the team worked on the ML for our wait time estimation, web application development, and circuit development. Sophie gave our design presentation at the beginning of the week, … Read More “Team Status Report for February 26th, 2022”
Dina Razek’s Status Report for February 26th, 2022
This week, I worked on setting up our web application. I built out the urls, the views, and started working on the HTML for each page. A form is being … Read More “Dina Razek’s Status Report for February 26th, 2022”
Sophie Sacks’s Status Report for February 26th
This week, I began by giving the Design Review presentation. I put a good deal of work into prepping for the presentation as well as presenting on Monday. For the … Read More “Sophie Sacks’s Status Report for February 26th”
Sam Lavelle’s Status Report for Feb. 26, 2022
This week, I finished constructing our circuit on a breadboard. I also added our logo to our website and design review presentation. I’m on schedule, but anticipate a possible delay … Read More “Sam Lavelle’s Status Report for Feb. 26, 2022”
Sophie Sacks’s Status Report for February 19th
This week, most of my focus went into the Design Review presentation since I will be presenting for my team. I mainly put work into the system specification for the … Read More “Sophie Sacks’s Status Report for February 19th”
Sam Lavelle’s Status Report for Feb. 19, 2022
his week, I designed our hardware implentation and gathered/ordered all necessary supplies. Any uncertainties were fleshed out in our weekly meeting, so now it’s ready to be built! I also … Read More “Sam Lavelle’s Status Report for Feb. 19, 2022”