Team Status Report for March 19th

This week, the team worked on the ML for our wait time estimation, web application development, and circuit development. We received feedback on our Design Report that helped us stay on track. We are on schedule with our project.

There were no changes to the existing design of the system. Below are some pictures showing our progress on the web application. All of the current components shown on the page are functioning.

Below is our updated Gantt chart. No major changes have been made to the schedule or lists of tasks necessary to complete the project.

Leave a Reply

Your email address will not be published. Required fields are marked *

*