Yuxin’s Status Report for 04/16

What did you personally accomplish this week on the project?

Made multiple modifications of the script that controls the LED strip.

Test delay and accuracy of ultrasound sensor subsystem. Test I/O with server. Discuss with team about OpenCV backup plan.

Is your progress on schedule or behind?

My progress is currently on schedule

What deliverables do you hope to complete in the next week?

I plan to finish testing of ultrasound/LED subsystems next week. And I’ll help with the OpenCV part if needed.

Leave a Reply

Your email address will not be published. Required fields are marked *