ruizhezh’s Status Report for 02/26

What did you personally accomplish this week on the project? Give files or photos that demonstrate your progress. Prove to the reader that you put sufficient effort into the project over the course of the week (12+ hours).

The week is still mostly comprised of prototyping work to help with the design doc;

I am starting to implement the framework of the parking lot management system as well as the navigation system, and making small design changes and new design decisions as my openCV counterpart continues to shed more information on car plate recognition;

Main work completed this week are:

  • Re-designed package structure for server application to ensure better class separation;
  • Significant progress on designing parking management part of application, as well as some implementation;
  • Worked with teammates to complete setup of raspberry pi workstation for ultrasound development;

Please track the current progress through the GitHub repository posted.

(To be added to the GitHub repository, please contact me via email)

 

Is your progress on schedule or behind? If you are behind, what actions will be taken to catch up to the project schedule?

I am on schedule for this week;

What deliverables do you hope to complete in the next week?

I am expecting to finish:

  • Designing Parking management part of the application;
  • Significant portions of the implementation of the management system;
  • Discussing backup plans in case openCV development failure; see team report for more information on this.