Team Status Report 4/23

This week we focused on testing and getting results to share on the final presentation. We also aimed to finalize all important integration between subsystems. We are still working on getting the modules to be powered by batteries but plan to have it done by this week.

Next week, while Kanvi focuses on delivering the final presentation, Neville and I will start thinking about our miniature version for the public demo.

Overall, we are on schedule according to our gantt chart!