This past week we each continued on working on our respective parts as well as coming together to get integration up and running. We now have the Bluetooth fully integrated and are working on smart contract integration. We put together our interim demo as well. We sorted through bugs which related to integration. We also fixed the bluetooth module which burned out. We are currently on schedule and this next week will consist of building the physical enclosure, finishing integration, and write out the algorithm. We have to change our algorithm though to account for variable acceleration positions. We plan on using the difference between the accelerometer readings.