Accomplishments this week
1. Migration of the Web Application to AWS
- For the project to be working on AWS, I performed some data structure edits and connected the local tracker program with AWS successfully
2. Prepared for final presentation and demo
- Went through the workflow that we will want to show in the final demo
- Prepared for necessary material that will be covered in the final presentation, redrawn the block diagram which illustrates the final system design.
Progress for schedule:
- On schedule
Deliverables I hope to accomplish next week:
- work on the demo video