Team Status Report 9/25

For this week, we followed our schedule/Gantt chart and attempted to do every thing on our list. Almost every single task was accomplished successfully, with details listed on our personal status reports, with the only hiccup being our AWS setup – the credits will be acquired by next week, and we have already looked into which AWS instance type would be most suitable for our group.

During class time, our entire group also performed peer review on all our classmates. We decided that Kunal would be presenting for the second presentation, and we also aim to address all of the concerns that were addressed during the Q/A session of our first presentation, as well as all feedback we received from TAs/professors through Slack.

As a team, we further discussed the model for our project, as that is a core part of the upscaling process. Reflecting on the feedback from Slack, as well as following our schedule, we also decided on a specific dataset and acquired the videos online from a database that provides it.

Looking towards next week, we are on track according to our schedule, and optimistic of continuing our positive trajectory. Next week, we begin trying to implement I/O with our acquired hardware, as well as preparing well for our design presentation. We will also begin writing code for the training part of our project in Python.

Leave a Reply

Your email address will not be published. Required fields are marked *