Team Status Update for 10/2
The team has been and will continue working on conducting trade studies on important components in order to finalize our BOM by Tuesday. We will also begin creating design documents such as block diagrams and schematics this week.
Potential risks for our coming week are:
- Not having a complete BOM by deliverable date
- We have built in slack time and a 2 week lead time in our schedule to manage the potential for this risk
No changes to our design have occurred yet (since it’s actively under design and thus nothing is set in stone). Our schedule is still in place and we’re still on track with the schedule.