Progress report March 8, 2018
Testing the capper, clamp design, and PCB testing
Progress report March 22, 2018
Testing the bottle weigher, received the stencil
Progress report March 29, 2018
Software and test program stuff
Progress report April 5, 2018
AVR studio
Progress report April 13, 2018
Core software written, overall mechanical drawing finalized
Progress report April 19, 2018
Assembly of rail mechanisms, tested ultrasonic sensor, ADC, and stepper code
Progress report April 26, 2018
Finished 4 rail assembly and tested horizontal bottle motion
Finished manual-mode program to run all
Progress report May 3, 2018
Finished manual-mode program to run all motors
Final Demo Videos
Click here to see refil in action!