Team Weekly Update | 4/26 Accomplishments This week we finished most of the final system testing, finalized our project presentation, and prepared for the upcoming demo. The pressure sensing system, BLE communication, calibration process, and app visualization are all complete
Team Status Report 4/19
Team Weekly Update | 4/19 Accomplishments This week we made major progress on integrating the full sensing system onto the bike and preparing for the final presentation. Zoe completed the transition of the force sensing system onto protoboards and rewired
Team Status Report 4/12
Team Weekly Update | 4/12 Accomplishments This week we focused on finalizing the next round of hardware updates and planning our verification and validation testing. A big part of this was discussing and iterating on a new sensor housing design.
Team Status Report 3/29
Team Weekly Update | 3/29 Accomplishments This week we focused on getting everything ready for the demo. We moved the bike and bike stand from Rita’s place to Zoe’s so we could work together in person. Being in the same
Team Status Report 3/22
Team Weekly Update | 3/22 Accomplishments This week, we attended the ethics lecture and continued to address key considerations, risks, and stakeholders related to our project. We also engaged in red teaming and we were able to provide additional risks
Team Status Report 3/15
Team Weekly Update | 3/15 Accomplishments This week, we worked on the ethics assignment, making sure we addressed key considerations related to our project and how it impacts users. It was a good opportunity to think through potential challenges beyond
Team Status Report 3/8
Team Weekly Update | 3/8 Accomplishments The past two weeks were focused on finishing up the design report and design review presentation. We spent a lot of time making sure everything was clear, well-organized, and covered all the technical details.
Team Weekly Update | All | 2/22
Team Weekly Update | All | 2/22 Project Risks & Management Significant Risks: – Ensuring Carolyn is fully prepared for the design review – OpenCV and calibration decisions pose a risk, as committing to a specific implementation too early may
Team Status Report 2/15
Team Weekly Update | All | 2/15 Project Risks & Management Significant Risks: – Ensuring Carolyn is fully prepared for the design review – OpenCV and calibration decisions pose a risk, as committing to a specific implementation too early may
Team Status Report for 2/8
Team Weekly Update | All | 2/8 Project Risks & Management Significant Risks: – Hardware compatibility issues, ensuring seamless communication between the Raspberry Pi and ESP32, especially over Bluetooth. – Processing power and latency concerns, particularly the Raspberry Pi’s ability