Team Weekly Update | All | 2/22

Team Weekly Update | All | 2/22 Project Risks & Management Significant Risks: – Ensuring Carolyn is fully prepared for the design review – OpenCV and calibration decisions pose a risk, as committing to a specific implementation too early may

rpaixao February 23, 2025February 23, 2025 Team Reports No Comments Read more

Zoe’s Status Report 2/22

Personal Weekly Update | Zoe | 2/22 Accomplishments This week, I spent 4 hours in mandatory lab time for peer reviewing and evaluating design presentations. It was useful to see what other teams were working on and get feedback to

zzwhite February 23, 2025February 23, 2025 Zoe's Status Reports No Comments Read more

Personal Weekly Update | Rita | 2/22

Personal Weekly Update | Rita | 2/22 Accomplishments Design Presentation Refinement and Research (6hrs): This was a bit of a lighter week, since my partner, Carolyn, was in charge of giving the Design presentation. Zoe and I spent the bulk

rpaixao February 23, 2025 Rita's Status Reports No Comments Read more

Carolyn’s Status Report 2/22

Personal Weekly Update | Carolyn | 2/22 Accomplishments Design Presentation Refinement and Research (6hrs): This week, I presented our Design Review, finalizing the presentation on Sunday by refining the quantitative design requirements, software specifications, and testing. I also spent time

carolyny February 22, 2025March 8, 2025 Carolyn's Status Reports No Comments Read more

Rita’s Status Report 2/15

Personal Weekly Update | Rita | 2/15 Accomplishments Device Integration Design and Research (5hrs): I spent my time this week researching different methods of attaching the sensors and microcontrollers to the bicycle. So far, we have decided to make a 3D

rpaixao February 16, 2025February 17, 2025 Rita's Status Reports No Comments Read more

Carolyn’s Status Report 2/15

Personal Weekly Update | Carolyn | 2/15 Accomplishments Design Presentation Refinement and Research (7hrs): This week I spent time refining and designing our presentation, ensuring it aligned with the provided guidelines and was well-supported by research, particularly on the software

carolyny February 16, 2025February 16, 2025 Carolyn's Status Reports No Comments Read more

Team Status Report 2/15

Team Weekly Update | All | 2/15 Project Risks & Management Significant Risks: – Ensuring Carolyn is fully prepared for the design review – OpenCV and calibration decisions pose a risk, as committing to a specific implementation too early may

zzwhite February 16, 2025 Team Reports No Comments Read more

Zoe’s Status Report 2/15

Personal Weekly Update | Zoe | 2/15 Accomplishments This week, I dedicated significant time to refining our design presentation (8 hours), ensuring it was well-structured, visually cohesive, and backed by solid research. I also contributed to the design report, integrating

zzwhite February 16, 2025February 16, 2025 Zoe's Status Reports No Comments Read more
  • Home Page
  • Project Summary & Intro
  • Proposal
  • Design Review
  • Final Project Documents
  • Status Reports

Status Reports

  • Individual Status Reports
  • Team Status Reports

Monthly Archives

  • April 2025 (12)
  • March 2025 (16)
  • February 2025 (8)
  • January 2025 (4)
Copyright © 2025 Team C4: Cyclify. All rights reserved. Theme Spacious by ThemeGrill. Powered by: WordPress.