Doreen’s Status Report for 2/24/24

  • This week, I worked on building the rack. This involved drawing the shapes for the frame on 1/2 inch plywood and cutting them out in the wood shop in Techspark. Since many pieces needed to be cut, and I did not have training to use the machines in the wood-shop, the only tools that were used were jigsaws and drills, making the process longer than initially thought.
  • My progress is only schedule according to the timeline. However, with multiple midterms in the upcoming week, it will be difficult to carve out time to finish building the rack. I hope to completely focus of this after my exams on Wednesday if I do not find time in the beginning of the week.
  • For next week, I hope to finish building the rack with my team member, so that we can begin adding the electronic components. I also hope to carve out time to learn how to use Coreldraw to design the gears that we will need to rotate the rack. I also plan on helping to write the design report.

Leave a Reply

Your email address will not be published. Required fields are marked *