- What did you personally accomplish this week on the project?
Following the plan to migrate CV and ML modules to the local iOS app, I was mainly responsible for getting the Swift version of code to work this week. I successfully made the mobile app running, showing 21 landmarks per hand as expected. However, I am still debugging the CoreML interface that should integrate the ML model we trained and the real-time mediapipe landmarks.
- Is your progress on schedule or behind? If you are behind, what actions will be taken to catch up to the project schedule?
I devoted quite an amount of time working on my task this week, but I am still a bit behind schedule. Since the set milestone and project deadlines are approaching, I will make sure to seek help if really stuck.
- What deliverables do you hope to complete in the next week?
CoreML integration
Testing with ML latency and accuracy