Team Status Report for 03/16

Our most significant risk is the still the PCB component that we decided to add to our system. Moreover, we have to postpone the building of xy motor system because Zipiao was not able to return to US this week.

We currently do not have any design change and we had a deeper understanding of our project by diving into the individual components and assembling them.

Schedule wise, as Zipiao was unable to return in time, we assigned Zipiao to do the webapp first during last week. And Sizhe and Shuailin was able to finish certifying that there are no interference problem between locking and detection system.

Next week, since Zipiao is likely coming back, we will mainly focus on integration with the gantry system and decide on the actual dimension of the outer housing.