Team Status Report for 4/22
The most significant risk that could jeopardize the success of the project currently are the accuracy of our wait time algorithm and how to transfer the data from our Jetson to our database SQLite. Now that Nii has almost finished his duties, he will be shifting over to help Chi optimize the algorithm to hopefully make the algorithm produce better results. Another risk to consider is whether or now we will be able to get the Jetson to transfer the data.We have already integrated the hardware and the backend software side so the very last step is to integrate it with the frontend side which communicate by transferring data through JSON. Since we have the Jetson hooked up to WiFi already, we will all be working together tomorrow to have this issue resolved very soon.
No changes were made to the existing design.
You may find our current schedule here.