We predict some trouble with the implementation of the backend of the web application. Because of this, the backend section may take a little bit longer than previously thought to complete. In the case that this happens, we will simplify some of the features of the web app, such as only displaying the current week’s statistics instead of being able to scroll to see all of the past week’s statistics as well.
We are also unsure about approaching the mechanical construction. We have a design in mind, but none of us have much experience with woodworking or anything like that. We plan to ask TAs and professors for guidance, and Techspark workers for help with the building process.
We did not make any changes to the existing design of the system. Currently, all of the parts of the project are more or less on schedule. We will be able to start working on integrating some systems together, such as the CV and hardware.
Some testing on inference time:
Fun with Jetson camera: