Aakash’s Status Report for 9/21/2024

This week involved delivering the proposal presentation and finalizing some of our project details. My role in the project was to work on the algorithm to determine the musicians’ timings. Other than working on this presentation I worked doing some cursory research onto how we we would integrate the FPGA and Raspberry Pi along with coordinating some logistics around recording the musicians.

I also setup the WordPress website and made sure everything was good to go on that end of things.

Is your progress on schedule or behind? If you are behind, what actions will be taken to catch up to the project schedule?

My progress is on schedule.

What deliverables do you hope to complete in the next week?

In the next week, I plan on researching Raspberry Pis and putting in a purchase order for one and beginning to record audio from the school of music performers and begin some cursory analysis of the audio recordings.