What are the most significant risks that could jeopardize the success of the project? How are these risks being managed? What contingency plans are ready?
The most significant risk as of now is that the system won’t be performant on a raspberry pi and that some pieces of music won’t be able to be processed. In order to mitigate these risks we always have the use of a laptop as a backup as we know the system works well on that and to limit the scope of the pieces we use for the demo. This will allow us to have a fully working demo no matter what and be able to show off the functionality of our system without working with unknowns.
Were any changes made to the existing design of the system (requirements, block diagram, system spec, etc)? Why was this change necessary, what costs does the change incur, and how will these costs be mitigated going forward?
No changes made at this time.