What did you personally accomplish this week on the project? Give files or photos that demonstrate your progress. Prove to the reader that you put sufficient effort into the project over the course of the week (12+ hours).
- This week, I looked into weighing the option of rotating the LCD screen versus keeping it in a horizontal display.
- Rotating the LCD is time costly (as it requires a nested for-loop) and could potentially put our latency past our requirements, but would be better for the physical design.
- I continued making progress on the design using the rotated LCD, including preparing a CAD model to do initial fit tests on.
- I began preparing to connect the power SHIM onto the pico, including doing research on what steps to take before/after connection.
Is your progress on schedule or behind. If you are behind, what actions will be
taken to catch up to the project schedule?
- I am slightly behind schedule, as I haven’t been able to print the glasses cases yet. To catch up with the schedule, I plan to do a short sprint tomorrow to finish the CAD and send the print job over to the TechSpark 3D printers.
What deliverables do you hope to complete in the next week?
- I hope to have a prototype of the glasses will all components attached, even if the LCD is in the incorrect orientation.
- I will be working with Alena and Kayla to standardize the method of communication between all components, including web app to the picos.