Meghana’s Status Report for 12/10/22

In the beginning of this week we were preparing for final presentations and running enough tests to be able to put baseline metrics on our presentation slides. It was my turn to present, so I spent extra time preparing and practicing my presentation. The presentation went well and the slides Read more…

By mkeeta, 2 years ago
Meghana's Status Reports

Meghana’s Status Report for 11/19/22

This week I made a lot of progress with the construction and hardware of the robot. The motor now runs well with the drill battery, 18V to 12V step down, and new Cytron Motor Driver.    In the beginning of the week things were a little bit iffy because we Read more…

By mkeeta, 2 years2 years ago
Meghana's Status Reports

Meghana’s Status Report for 11/12/22

This week we had demo’s during class. So we started the week by preparing for these demos. We demonstrated the intake mechanism working with a drill and talked more about the construction of the robot and showed our bottle detection algorithm and our iRobot moving towards the bottle.    After Read more…

By mkeeta, 2 years ago
Meghana's Status Reports

Meghana’s Status Report for 11/5/22

This week I made a lot of progress on the construction of the robot with Serena’s help. We took the robot apart so that we could put the lexan we newly ordered underneath for the water bottle storage area. Before attaching the new piece of lexan I had to get Read more…

By mkeeta, 3 years ago
Meghana's Status Reports

Meghana’s Status Report for 10/29/22

This week I made a lot of progress with implementing the design of the robot. In the beginning I worked with Professor Haider on cutting holes in our piece of lexan to go on top of the faceplate. She showed me how to use a Hole saw and we cut Read more…

By mkeeta, 3 years ago
Meghana's Status Reports

Meghana’s Status Report for 10/22/22

These past two weeks I tested the robot intake with Serena and Mae, worked on ordering more necessary parts for the robot, updated the CAD to add passive wheels and worked on the Design Report. For the robot intake, I wanted to figure out a way to test it out Read more…

By mkeeta, 3 years ago
Meghana's Status Reports

Meghana’s Status Report for 10/08/22

After the last status update last weekend, I CADed the basic parts of the robot. Below are pictures of the CADed robot from different angles. While I was CADing the robot, I also had to figure out exactly what parts to use and do research on one part over another. Read more…

By mkeeta, 3 years3 years ago
Meghana's Status Reports

Meghana’s Status Report for 10/01/22

This week after speaking with Tamal, we decided to pivot away from building a robot from scratch and using an iRobot as a base instead. In the beginning I was struggling with mounting on the iRobot and it being more restricted, but then came around to the idea after more Read more…

By mkeeta, 3 years ago
Meghana's Status Reports

Meghana’s Status Report For 9/24/22

In the beginning of the week, Mae and I helped Serena with the Project Proposal Slides. During the slide preparations I made a rough Figma design of what the robot will look like. In the upcoming week I plan to fully CAD the design to understand the practicality of it Read more…

By mkeeta, 3 years3 years ago
Recent Posts
  • Serena’s Status Report for 11/10/22
  • Team Status Report for 12/10/22
  • Mae’s Status Report for 12/10/22
  • Meghana’s Status Report for 12/10/22
  • Meghana’s Status Report for 12/3/22
Recent Comments
    Archives
    • December 2022
    • November 2022
    • October 2022
    • September 2022
    Categories
    • Mae's Status Reports
    • Meghana's Status Reports
    • Serena's Status Reports
    • Uncategorized
    • Weekly Status Reports
    Meta
    • Log in
    • Entries RSS
    • Comments RSS
    • WordPress.org
    • Design Review
    • Final Project Documents
    • Introduction and Project Summary
    • Proposal
    • Weekly Status Reports
    Hestia | Developed by ThemeIsle